An introductory example (Knocker, Blaster) -Vol.1-
Recently, we have many inquiry for the knocker and Blaster from many visitors.
So, while introducing some fitting (introduction) examples of these machines adopted in various places, it reports also about the situation of a fitting before / after
So, while introducing some fitting (introduction) examples of these machines adopted in various places, it reports also about the situation of a fitting before / after
Food factory

- Site
- Food factory
- Model
- Air knocker/RKV40P(S)
- Specification
- For the purpose of omitting welding operation because of an SUS made tank, the knocker was equipped with the gusset plate for anchoring, it installed by the bolt anchoring, without performing welding operation, very short time of period of installation work was completed.
- Situation before adoption
- Since cleaned rice in the hopper adhered to a wall surface by humidity, and an exhaust of rice was not able to be performed when required, customer decided to aim at a smooth exhaust by a knocker's striking force.
- The present situation
- By a knocker's striking force, adhesion of a hopper wall surface is destroyed, a smooth exhaust is enabled, and it contributes to improvement in productivity.
Ready-mixed-concrete plant

- Site
- Ready-mixed-concrete plant
- Model
- Direct Blaster /EDB4-130T type.
- Specification
- Sand silo diameter 6mx height of 8m.
- Situation before adoption
- In the case of the sand containing the moisture, when discharging the aggregate (fine sand) stored in the sand silo, remains occurred within the silo, when required for manufacture of a ready mixed concrete, an exhaust of an aggregate was not performed.
- The present situation
- According to the propellant force of Blaster, the remains in a sand silo are destroyed, a smooth exhaust of an aggregate is enabled, and it contributes to planned ready-mixed-concrete manufacture.
Moreover, by introduction of twin type Blaster, the cost cut of Blaster and shortening of a installation work were attained, and construction expense could also be lower.
Sugar factory

- Site
- Sugar factory
- Model
- Air knocker/RKV80P
- Situation before adoption
- According to the characteristic adhesion of sugar, the trouble had occurred by adhesion of a hopper wall surface. The present situation. Although the adhesion to a wall surface originally occurs at a humid season, the smooth exhaust is enabled by giving a periodical striking force by knocker installation.
- The present situation
- Originally, the adhesion to the surface of wall occurs at a humid season. However, smooth discharge was achieved by giving a periodical impact by knocker installation.
Refuse incineration works

- Site
- Refuse incineration works
- Model
- Air knocker/RKV100P
- Specification
- The heat-resistant specification (140 degrees C) was adopted, also by using extended anchoring base, and the heat transfer from a hopper is reduced.
- Situation before adoption
- The ash generated after incinerating common garbage adhered to the hopper wall surface, and had caused the capacity down of a boiler.
- The present situation
- Adhesion of a wall surface was canceled by a knocker's striking force, and the ability improvement of a boiler is measured.